Thursday, March 29, 2007

Garden consultation

Already last year had we the seminar of building of houses of the country Nö. visited, there we have experienced that the country Nö against a small self participation both building of houses and a garden consultation offer. We have the building consultation before longer time taken in Ansspruch, today were already our date for the garden consultation. We wanted to already specify this consultation before commencement of construction, there we now the area process would like around that with the excavation and with the building to consider to be able. I can recommend this consultation only to everyone, which brought Planerin (Fr. Elizabeth Höfner) a great many good ideas in, above all which concerns the organization of the embankments, to convert we have myself made nearly all your suggestions. We get the garden plan developed in the discussion within the next two weeks dispatched by it.

Monday, March 19, 2007

bad messages of the stress analyst…

Today the stress analyst (Mr. Pribek from Vienna) was with a restaurant inspection with us locally. So far I had always assumed that the Gewölbekeller under the old house could become a problem, but that was far been missing. A well trained Tonnengewölbe that is practically no “horizontal thrust” developed and therefore no problem makes, but the true problem is the foundation of the old house! Our sample excavation has devoted that it built is as if no cellar would be under it and if one digs 2 meters beside it an excavation exists the danger it slips away. The stress analyst strikes a “venture” before i.e. along the house is in sections up-dug and the foundation to to the cellar foundation extended. Thus I can adjust myself to a few thousand euro extra costs: - (

Thursday, March 1, 2007

Submission at the municipality

With more easily delay our submitting plans at the Fr. before Whitsuntide (13 became. May 2005) finished. Since we were on the day already on short vacation, my wife got the plans only at the Di. 17. and today, Mi. 18. , We submitted May. The plans in the apron already several times with the board of works leader of the municipality Himberg, Hrn. Ruzak, co-ordinated therefore us assured which we permission are surely and fast gotten. We were cared for by Hrn. Ruzak very friendly and competently, I would wish ourselves at all authorities such a service to get.Since only few neighbors party position have, I them all know and none suffers a disadvantage by our house surely no objection raised. Thus it will give only a shortened procedure without building negotiation. As per information of the municipality the building permit should be in approx. 4 weeks there.